Dan Gallagher, Ph.D.
Dr. Dan Gallagher: served as Executive
Editor for the Monroe County Environmental Story in 1991
while working with the Newfound
Harbor Marine Institute at Seacamp. Since
that time he became a founding member of the Pigeon Key Foundation,
and currently serves as Education/ Museum Director for the Pigeon
Key Foundation. Publications include
Pigeon Key and the Seven-Mile Bridge (1996), and editorship
of the Teacher Activity Guide for the Monroe County Environmental
Story (1996).
The Overseas Railroad (officially
known as the Florida East Coast Railway Key West Extension) lay
atop many miles of fill and bridges built by the F.E.C. Ry. Construction
Division between 1905 through 1912. This long right-of-way passed
down through the Keys, much of it forming the current corridor
now called U.S. Highway One. The F.E.C. Ry. bridges served first
as a highway for trains, then later for motor vehicles. Today
they are used for fishing piers, scenic overlooks, and exercise
areas for visitors and residents.
The bridges themselves are significant
contributions to the Florida Keys built environment. In total
distance the 42 F.E.C. Ry. bridges covered 17.98 miles. Estimates
vary on the total cost of construction, ranging between $20,000,000
to $33,000,000, all privately financed by the F.E.C. Ry.
Bridges are made of two parts: piers
and spans. Piers are upright fabrications that anchor to the bottom
of the sea and rise to support the upper portions. The upper sections
(or spans) cross between the piers to form the roadbed. The piers
for all of the F.E.C. Ry. bridges were built in the same fashion,
but the upper spans varied depending on the conditions.
Water depth dictated how high the
bridges must stand above the water. In shallow waters, the F.E.C.
Ry. engineers designed low bridges made of concrete arches. Deeper
waters (which generate larger waves and storm surge in hurricane
conditions) required taller bridges. Three of the bridges (the
Long Key Bridge, the Seven-Mile Bridge and the Bahia Honda Bridge)
passed over deep water, and each bridge was more than 20 feet
above mean high tide. The Long Key bridge was built with 180 spandrel
arches; the two other tall bridges were made with steel spans.
Spandrel Bridge Construction
Most of the East Coast Extension
bridges were built with spandrel arches. These graceful arches
do not show us much about the supporting piers; these are submerged.
The spandrel arch bridges, while simple in form and graceful to
the eye, required several complex steps and concrete forms in
their construction process.
Before any spandrel pier forms were
set in place, construction workers and divers cleaned off the
layer of sand and sediments built up on top of the coral rock
that underlies the Florida Keys. This coral limestone bedrock
provided an excellent substrate for concrete construction -- it
is a solid mass of rock that affords a good anchor for the piers
supporting the bridge. At this time the workers also drove many
wooden pilings in the footprint where the pier was to be built.
They then brought in pre-fabricated cofferdams -- boxes of wood
much larger than the pier -- and set these in place on the bottom.
These cofferdams had no bottom, and, when in place, were full
of water at this time.
After the cofferdam was anchored
in position, workers gently pumped concrete into the bottom of
the form. The sides of the cofferdam contained the concrete, and,
when it reached a thickness of two feet, the first pour was complete.
The concrete hardened underwater in a few days, firmly holding
the wooden pilings driven into the bedrock, and making a "seal"
to the bottom of the bay. When the concrete cured, workers pumped
out the water captured in the cofferdam, and began to build the
next part of the pier on this seal.
The second stage molded the lower
section, the rising part of the pier. The lower section forms
were partially built on land and assembled inside the now-dry
cofferdam. These forms shaped the concrete with a spreading set
of "ears" at the upper part. Steel reinforcing rods were used
extensively in this construction, and protruded from the upper
part of the lower section pier as may be seen in the photo of
the completed lower section with all forms removed. This photo
also shows gangs of pilings to be used to support the next forms.
The span portion of these spandrel
arches was built upon these piers. The first form used for the
spandrel arch was termed an arch ring mold, and was also prefabricated
on land. These arch ring molds were transported by barge to the
job site, jockeyed in place, and positioned between the protruding
"ears" of the lower section. As the tide rose, the arch ring mold
was gradually forced up to meet the "ears", and was then wedged
into place on supporting pilings as shown in the photo.
After the arch ring mold was braced,
workers began building wall forms for the spandrel arches. These
were built to be re-used, as were all of the forms for the bridges.
Again, they placed tons of reinforcing steel within each arch,
tying the spandrel spans to the lower section piers. At this time
they also put a center form inside the growing spandrel form.
This form kept concrete from the middle of the spandrel arches;
they were hollow inside. This hollow area was later filled with
coarse gravel. Workers layed ties and track directly on this ballast
rock bed; the gravel cushioned the train weight from the concrete
arches. The summary graphic on the following page shows these
steps in bridge construction.
Tall piers and steel spans
About five miles of the Seven-Mile
Bridge were built with tall piers and steel spans. These spans,
termed steel deck plates, were each 80 feet long, except for a
small section at the curve over Pigeon Key, where they are 60
feet in length. The tall piers are graceful, tapered, solid concrete
fabrications with steel reinforcing.
Initial steps for building these
tall piers were much the same as for the spandrel piers below
the water line. Again, they used cofferdams, poured a seal, then
poured a lower section below the water level. When this was completed,
workmen built upper forms on top of them. These piers were then
ready for the steel deck plates to be set in place on large pads
that distributed the 19-ton weight of each deck plate. The deck
plates were then tied together with a network of angle iron crossmembers.
While the deck plates came prefabricated from the American Bridge
Company, all of the assembly was done "in the field" by ironworkers
who riveted the parts together.
The Bahia Honda Bridge was also
built on tall piers -- some of them more than 40 feet below the
surface of the water. While steel deck plates were used for the
approaches at each end, most of the Bahia Honda Bridge is built
from trusses. The train passed through the trusses on track laid
inside the bridge.
A few notes on the bridges of the F.E.C. Ry. Key West
Extension...
Building the Florida East Coast
Key West Extension was a massive undertaking, financed through
a private corporation, not with government funds. It was also
massive in the scope -- eighteen miles of bridges, more than a
hundred miles of track laid on fill in an environment hostile
with insects, heat and hurricanes. All the supplies had to be
brought in from outside...rock, sand, steel, cement and water.
More than 20,000 workers contributed to the project during the
construction years. It was an incredibly labor-intensive task,
completed with strong backs and relatively unsophisticated tools.
Most of the vessels and all of the machinery (cranes, cement mixers)
were driven by steam engines.
The bridges of the great Key West
Extension were built to last. It may be noted that none of the
F.E.C. Ry. bridges have ever been damaged by hurricanes -- those
that are no longer in place have been removed by man in order
to build our modern highway bridges. The three great bridges...the
Long Key Bridge, portions of the Seven-Mile Bridge, and the Bahia
Honda Bridge...are listed on the National Register of Historic
Places. It is reasonable to assume that these great bridges will
long be a part of the Keys’ built environment. As they stand today,
they afford opportunities for fishermen, recreation, and offer
a rich niche for marine life as structure and habitat on the bottom
of the inlets that connect the Atlantic with Florida Bay.
FIGURE CAPTIONS
Fig. 1. Cofferdams. Three are
in place in the foreground; a fourth is lowered by a crane to
seat on the bottom of Florida Bay.

Fig. 2. Pumping sea water from
the cofferdam before beginning construction of the lower section
form.

Fig. 3. Lower section form under
construction inside the cofferdam.

Fig. 4. Lower section completed.
Note the reinforcing steel rods protruding to tie into the next
stage.

Fig. 5. Three spandrel arches
of the Long Key Viaduct under varying stages of completion. At
the left, a barge is bringing an arch ring form to place between
the completed lower sections. The central part shows an arch ring
form braced in place between the piers. The rightmost part of
the picture shows the side forms resting on the arch ring form.

Fig. 6. Tall pier forms. This
photo is from a F.E.C. Ry. postcard series.

Fig. 7. Workmen assembling the
crossbraces for the steel deck plates as bridge work progresses
on the Pigeon Key Trestle.

Building the Bridge Piers...
Steps for building a spandrel
arched pier...
Step 1. Cofferdam forms
are placed in a square on the bottom. The central pilings go through
the bedrock to hold the completed block in place. Workers drop
sandbags around the cofferdam to stabilize the form. (the right
side is not shown in these diagrams.)

Step 2. Concrete is piped
into the cofferdam form to make a "seal." When it hardens, the
pilings will tie the seal to the next level to be poured.

Step 3. Workers use large
pumps on barges to pump water from the cofferdam. They then build
the lower section form inside the dry cofferdam. This form is
for a spandrel bridge pier.

Step 4. Cofferdam and
form are removed. The steel reinforcing rods protrude to tie into
the upper form (see below).

Assembling the arched
spans into a bridge...
Arch ring forms for the underside
of the upper sections of the spandrels are brought by barge to
the completed piers.
When located properly, the wooden
forms are braced in place on a scaffold of pilings (not shown).
Side forms are added to the arch
ring forms to shape the outside walls of the spandrel. These forms
were re-used if they could be taken apart without damage.
